Guildford Train Station Multi-Storey Car Park: Wall Joint Sealing
From September to November 2024 we sealed roughly 1,250 linear metres of vertical and horizontal concrete wall joints at a train station multi-storey car park in Guildford, reaching them by boom lift, crane with man and basket, and scaffold tower.
- Project
- Guildford train station multi-storey car park
- Our scope
- Vertical and horizontal concrete wall joints, roughly 1,250 linear metres
- Sealant
- Arbo MP20 modified polymer, with bond breaker tape and primer
- Dates
- September to November 2024
A multi-storey car park beside the railway
The Guildford car park is a multi-storey car park at a train station, and our package was the concrete wall joints: the vertical and horizontal joints between the wall panels, roughly 1,250 linear metres in total. We carried out the work from September to November 2024.
A multi-storey car park is mostly open to the weather, so its outer walls take rain and wind day after day. The joints between the wall panels are where water would find a way in, and where the concrete moves most as the seasons change. A sealed joint that stays bonded and flexible protects the structure and keeps the walls looking tidy.
Getting the access right and leaving a tidy, consistent finish matter as much on a job like this as the sealant itself.
Vertical and horizontal wall joints
What we sealed at the Guildford car park:
- Vertical concrete wall joints.
- Horizontal concrete wall joints.
- Roughly 1,250 linear metres across the structure.
- Completed between September and November 2024.
Because the same joint detail runs along the whole structure, a set method matters: it keeps the finished lines consistent from one bay to the next.
Four steps for every joint
Cleaned of dust
Each joint was cleaned of dust first, so the primer and sealant had a clean concrete face to bond to.
Bond breaker tape
Bond breaker tape was fitted in the joint, so the sealant is held on the two sides and not on the back of the joint.
Primed
The joint faces were primed before sealing to help the sealant grip the concrete.
Sealed and tooled
The joints were sealed with Arbo MP20, a one-part modified polymer sealant, and tooled to a smooth finish.
Three ways to reach the joints
A multi-storey structure cannot be sealed from one position, so we used the access method that suited each part of the car park. On this job, access was by:
- Boom lift: a movable platform that can be driven along the wall and held at the joint.
- Crane with man and basket: a basket lifted into position beside the joints.
- Scaffold tower: a stable platform for close-up work at the joint.
Our team holds IPAF 3a/3b cards for work at height, and risk assessments and method statements (RAMS) are available on request.

Insured & pre-qualified
For homeowners, builders and main contractors.
- £10m Employer’s LiabilityInsurance cover
- £5m Public Liability & Professional IndemnityInsurance cover
- Constructionline Silver member

- NVQ Level 2Sealant Applicator
Over 20 years in construction
Products we use
Sealants and adhesives we use on site.
Brand names and logos are trademarks of their respective owners and are shown to identify products we use. No endorsement is implied.
The Guildford car park joints



Arbo MP20 on concrete wall joints
Arbo MP20 is a one-part modified polymer sealant. It is ready to use from the cartridge, so there is nothing to mix while working from a basket, and modified polymer sealants are widely used on concrete because they stay flexible and cope with weather exposure.
At the Guildford car park the sealant went into a joint that had been cleaned, taped and primed, then tooled to a smooth finish. The tooling matters twice over: it presses the sealant against both joint faces for a good bond, and it leaves a neat line that sheds water.

More concrete joint sealing
Wall joints, movement joints and floor joints in concrete are part of our regular work for main contractors and developers. Read more about what we do:
concrete joint sealing · structural movement joints · precast concrete joint sealing · expansion joint sealing · commercial mastic contractor · the Multiversity Project in Blackpool · all our projects
About this project
What did Pioneer Sealants do at the Guildford car park?
We sealed the vertical and horizontal concrete wall joints at a train station multi-storey car park in Guildford: roughly 1,250 linear metres in total, between September and November 2024.
How were the Guildford joints prepared and sealed?
Each joint was cleaned of dust, fitted with bond breaker tape and primed. It was then sealed with Arbo MP20, a one-part modified polymer sealant, and tooled to a smooth finish.
How did your team reach the joints on a multi-storey car park?
Access was by boom lift, crane with man and basket, and scaffold tower. Different parts of a multi-storey structure call for different access, so we used all three.
Do you seal joints on car parks and other concrete structures?
Yes. We seal wall joints, movement joints and floor joints on concrete car parks and frames. Send drawings or photos to office@pioneersealants.co.uk, or call 01234 607 252, and we will come back with questions and a quote.
Planning a car park or concrete frame project?
Pioneer Sealants brings over 20 years in construction to every sealing package. Send drawings or photos to office@pioneersealants.co.uk or call 01234 607 252.